Alvin ISD E.C. Mason Replacement Elementary School

← BACK TO ALL BIDS
Bid Date: July 16, 2019
Owner: Alvin ISD
Lead Estimator: Kevin Hollenbeck
Phase: Past Projects
Location: Manvel, Texas between FM1128, Lewis Ln, School Road, and Large Ave, 77583

A. The Project consists of construction of a 2-story 103,000 SF new E.C. Mason Elementary School Replacement and related sitework in Manvel, Texas between FM1128, Lewis Ln, School Road, and Large Ave, as indicated on the Contract Documents prepared by Stantec Architecture and consultants, dated June 24, 2019.

B. The Work consists of Civil, Landscape, Structural, Architectural, Mechanical, Electrical, Plumbing, and Fire Protection requirements as indicated in the Project drawings and specifications.

C. There will be roadwork on FM1128 and School Road that will be by a separate contract. Close coordination with that work will be required.

REQUIRED COMPLETION DATES:
A. The Work shall be conducted according to the following schedule to ensure that the Owner has sufficient opportunity to ready the facility for occupancy and permit an orderly transfer of personnel, furnishings, and equipment.
1. Start Date for On-Site Construction: Approximately September 1, 2019
2. Project Substantial Completion Date: On or before December 1, 2020

BIDDING SCHEDULE:
• Senior Estimator: Kevin Hollenbeck
• Addendum #01: 6/28
• Pre-Bid Meeting: 7/2 @ 1:30 PM
Alvin ISD Transportation Center at Heritage Complex (behind Freedom Field)
4411 Davenport Parkway (County Road 64)
Iowa Colony, Texas 77583
• Last day for bidder RFI’s: 7/9 Send all RFI’s to khollenbeck@pogueconstruction.com
• Addendum #02 (last): 7/10

Bid Day: July 16, 2019

Bid Time: 2:00PM

Bids Delivered to: bid@pogueconstruction.com

← BACK TO ALL BIDS